Large company in the pulp sector, located in the interior of Minas Gerais, in the process of expanding its manufacturing facilities. To ensure operational safety, energy quality performance, and energy expansion, it was decided to elevate the voltage class by implementing a Power Substation and a 13 km High Voltage Distribution Line to meet an average consumption of 12 MW.
Solution
- Elevation of voltage class with the implementation of a power substation and high voltage distribution line of 13 km;
- Long-term contracting of electricity from sustainable sources, with origin certification;
- Management and representation at CCEE and Regulatory Bodies;
- Voltage reduction services through substations.
The IBS Energy Group has assumed all responsibilities for implementing the solutions and provides its own assets to serve the Client.