Brazilian auto parts manufacturer located in the capital of São Paulo, facing quality issues in electricity supply (frequent voltage fluctuations and interruptions), and flooding in the internal underground distribution network, causing production stoppages. The solution was to transfer the underground network to overhead and elevate the voltage class to meet an average consumption of 3.65 MW.

Solution

Reduction of downtimes (to less than 1% of historical incident s), with economic gains in energy expenses between 15% and 25% since the implementation of the solution.

One Response

  1. Excellent beat ! I wish to apprentice while you amend your website,
    how could i subscribe for a blog site? The account helped me a acceptable deal.
    I had been a little bit acquainted of this your broadcast provided bright
    clear idea

Leave a Reply

Your email address will not be published. Required fields are marked *